Delivery schedule

Not one of the seventeen Dholera records carries a declared completion date, so the question every contract register exists to answer, what slipped and by how long, cannot be answered from published sources as at 2026-08-04. What can be measured is mobilisation, the days between award and starting on site. Six contracts support it, and the range runs 28 to 105 days with a median of 61.

Declared due dates in the whole dataset0of 17 records
DICDL AR 2024-25, DICDL AR 2023-24, live tender page
Median mobilisation61days, 6 contracts
DERIVED from two printed dates
Longest run since award with no completion published628days, as at 2026-08-04
DERIVED from the printed award date
Percentage complete figures published0for DICDL’s own eight projects
Declared gap, AR 2024-25
1.0

Programme chart

2025-012025-042025-072025-102026-012026-042026-07Integrated Healthcare Facility53 DFood Court28 DIntegrated School105 DAccommodation Facilities for Investors28 DFire Station70 DTent City61 DResidential and Commercial Mixed-Use DevCorporate 3-Star HotelSOLID BAR: AWARD DATE TO CONSTRUCTION START, DAYS. HATCH: NO COMPLETION DATE PUBLISHED. YELLOW RULE: 2026-08-04.SOURCE: DICDL 9TH ANNUAL REPORT 2024-25, PP.22-29 AND P.100. UNIT: DAYS.
  • Award to construction start
  • No completion date published
  • Today rule, 2026-08-04

Every bar starts on a date printed in the DICDL 9th Annual Report 2024-25 at pages 22 to 29. The hatched band is not a forecast. It marks the part of each programme for which no source publishes anything at all. Unit: days. Tag: OFFICIAL. Last verified 2026-08-04.

2.0

Delivery schedule

SCH-03 / DELIVERY AGAINST DECLARED DATES / REV A / 2026-08-04
Row pitch
Award date, construction start, mobilisation and the empty due date column. Source: DICDL annual report 2024-25 and the DICDL live tender page
No.ItemWorkAward dateISOSite startISOMobilised indaysDeclared dueISOSince awarddaysState
Contracts where both dates are printed, mobilisation measurable
01Food Court2025-05-072025-06-0428not published454UNDER CONSTRUCTION
02Accommodation Facilities for Investors2025-03-272025-04-2428not published495UNDER CONSTRUCTION
03Integrated Healthcare Facility2024-12-162025-02-0753not published596UNDER CONSTRUCTION
04Tent City2025-03-272025-05-2761not published495UNDER CONSTRUCTION
05Fire Station2025-02-282025-05-0970not published522UNDER CONSTRUCTION
06Integrated School2025-02-282025-06-13105not published522UNDER CONSTRUCTION
Awards where at least one date is missing, mobilisation not measurable
07ABCD Buildingnot publishednot publishedn/anot publishedn/aIN DISPUTE
08Water Treatment Plantnot publishednot publishedn/anot publishedn/aTERMINATED
09Residential and Commercial Mixed-Use Development2024-11-14not publishedn/anot published628UNDER CONSTRUCTION
10Corporate 3-Star Hotel2024-12-24not publishedn/anot published588UNDER CONSTRUCTION
11Service Area Buildingnot publishednot publishedn/anot publishedn/aSTATUS NOT PUBLISHED
Tenders open for bids, counted down to the closing date
12Service Area Buildingnot awardednot awardedn/a2026-08-06n/aOPEN, NOT AWARDED
13Plot Boundary Fencing, rate contractnot awardednot awardedn/a2026-08-10n/aOPEN, NOT AWARDED
14Desalination DPR, consultancynot awardednot awardedn/a2026-08-13n/aOPEN, NOT AWARDED
15CETP, 20 MLDnot awardednot awardedn/a2026-08-20n/aOPEN, NOT AWARDED
16Accommodation Facility, operationsnot awardednot awardedn/a2026-08-20n/aOPEN, NOT AWARDED
17SWRO Desalination Plant, 50 MLDnot awardednot awardedn/a2026-09-03n/aOPEN, NOT AWARDED
Source: DICDL 9th Annual Report 2024-25 (audited, signed 2025-08-22) for every OFFICIAL row; cablecommunity.com trade report for the single REPORTED row. All rows last verified 2026-08-04 against the cited page.

The declared due date column is empty on every row of this table. That is the finding, not a formatting error. Days since award is DERIVED by subtracting the printed award date from the site build date of 2026-08-04.

3.0

Why the due date column is empty

Three separate sources were checked and none of them publishes a date

  • The DICDL 9th Annual Report 2024-25 devotes a page each to eight projects. Each page gives contractor, award basis, award date, cost, plot and built up areas and a construction start date, and each ends by describing the work as currently underway. None gives a duration, a target date or a percentage complete.
  • The NICDC and DPIIT Delivery Monitoring Unit reports do name EPC contractors and letter of award dates, but only for other corridor nodes. For Dholera they record that trunk infrastructure is complete and that the Government of India approved packages worth Rs. 2,784.83 crore across five packages, with no contractor, no per package value and no date.
  • The procurement portals returned nothing usable. The nProcure awarded tender API answered with zero records for DICDL and also zero for all clients, which means the capture failed rather than that no awards exist. That distinction is preserved on the method sheet instead of being reported as an empty result.

The single completion period anywhere in the dataset is 545 days on the Service Area Building record, and that record is trade press rather than government, and its award date is unknown, so even there a due date cannot be calculated. The record is kept and flagged rather than dropped.

SHEET SCH-03
REV A
DATE 2026-08-04
SOURCE DICDL AR 2024-25 pp.22 to 29