Dholera Contracts
11 awards with a named winner / 6 tenders still open / Updated 2026-08-04

Which companies won government work at Dholera, and for how much

Fire Station

This is a job DICDL is paying a contractor to build. Fire Station was awarded to M/s Aditya Infrabuilcon Pvt. Ltd. on 2025-02-28 at a stated ₹20.12 Crore. The record is marked OFFICIAL, which means it comes from a signed, audited annual report. No completion date is published for this contract anywhere, so nobody can say whether it is running on time or late. Everything on this page is taken from dicdl_ar25.pdf, page 26.

Award value20.12INR crore
Award date2025-02-28ISO
Construction start2025-05-09ISO
Scheduled completionno datanot published in any source
01

Every published field on this award

Every published field for the Fire Station award. Source: DICDL annual report and the dataset field list

Every published field for the Fire Station award. Source: DICDL annual report and the dataset field list
No.ItemFieldValue as recorded
01Work as described in the sourceFire Station, Dholera - construction work. 11 garages; plot area 8,793.63 sq m; built-up area 3,001 sq m.
02Specificationfire station with 11 garages
03Awarded to, as printedM/s Aditya Infrabuilcon Pvt. Ltd.
04Award basisItem Rate contract
05Project management consultantM/s TPF Engineering Pvt Ltd.
06Value as printed₹20.12 Crore
07Value unitINR crore
08Award date as printedFebruary 28, 2025
09Completion periodnot published
10Tender reference numbernot published in any source opened
11Pre-bid estimated valuenot published in any source opened
12Status as recordedUnder construction; construction started May 09, 2025
13Status as at2025-03-31 (FY2024-25 annual report, signed 10.11.2025)
14Record typeOFFICIAL
15Source documentdicdl_ar25.pdf, page 26
16Plot area8,793.63 sq m
17Built up area3,001 sq m

Source: dicdl_ar25.pdf, page 26. Record type OFFICIAL. All rows last verified 2026-08-04 against the cited page.

02

What the document actually says

Quoted from the document, not paraphrased

The Fire Station project construction work was awarded to M/s Aditya Infrabuilcon Pvt. Ltd. on an Item Rate contract basis. The award date was February 28, 2025, with a project cost of ₹20.12 Crore. The Fire Station project spanning across a plot area of 8,793.63 Sq.Mt. with a built-up area of 3,001 Sq.Mt. M/s TPF Engineering Pvt Ltd. serves as the Project Management Cons

Quoted from dicdl_ar25.pdf, page 26. Record type OFFICIAL. Retrieved 2026-08-04. The quotation is truncated exactly where the extraction truncated it and has not been tidied.

Only award in this set on an Item Rate basis rather than EPC. Value is stated as 'project cost'. PMC: M/s TPF Engineering Pvt Ltd.

03

How long the winner took to start

What can and cannot be measured here

The winner took 70 days from award to starting on site, measured by subtracting the award date from the construction start date, both of which the annual report prints. That is the only delivery measure this record supports. Because no completion date exists on the record, the work cannot be described as running late or running early by anyone, including DICDL.

Across the register, six of eleven awards carry both an award date and a construction start date, and none of the seventeen records carries a completion date. The comparison view for all of them is on the delivery schedule.

This is the only award held by Aditya Infrabuilcon Pvt. Ltd. in this register. Its sheet is at Aditya Infrabuilcon Pvt. Ltd..

Source dicdl_ar25.pdf
Checked 2026-08-04
04

What is missing from this record

What is missing, stated plainly

  • GAP 01No tender reference number is published against this award in any source opened, so it cannot be joined to a tender notice.
  • GAP 02No pre-bid estimated contract value is published, so the bid against estimate variance cannot be computed.
  • GAP 03No contract duration and no scheduled completion date are published, so this contract cannot be shown as early, on time or late.

These gaps are taken from the dataset’s own declared gap list, filtered to the fields that are null on this record. They are not inferred. The complete list of seventeen contract gaps and eleven financial gaps is on the method sheet.

PUBLISHED2026-08-11
VERSIONC
HOW SOLID IS THISUNDER CONSTRUCTION
WHAT THIS PAGE ISFire Station
WHERE THE FIGURES COME FROMdicdl_ar25.pdf
AWARDED TOM/s Aditya Infrabuilcon Pvt. Ltd.
RECORD TYPEOFFICIAL