Integrated School

This is a job DICDL is paying a contractor to build. Integrated School was awarded to M/s Build Well Engineers on 2025-02-28 at a stated ₹27.99 Crore. The record is marked OFFICIAL, which means it comes from a signed, audited annual report. No completion date is published for this contract anywhere, so nobody can say whether it is running on time or late. Everything on this page is taken from dicdl_ar25.pdf, page 24.

Award value27.99INR crore
Award date2025-02-28ISO
Construction start2025-06-13ISO
Scheduled completionno datanot published in any source
01

Every published field on this award

Every published field for the Integrated School award. Source: DICDL annual report and the dataset field list

Every published field for the Integrated School award. Source: DICDL annual report and the dataset field list
No.ItemFieldValue as recorded
01Work as described in the sourceIntegrated School, Dholera - construction work. CBSE/IB standards, Nursery to 12th Standard; plot area 34,529 sq m; built-up area 6,082.11 sq m.
02SpecificationCBSE/IB standards, Nursery to 12th Standard
03Awarded to, as printedM/s Build Well Engineers
04Award basisEPC
05Project management consultantM/s TPF Engineering Pvt Ltd.
06Value as printed₹27.99 Crore
07Value unitINR crore
08Award date as printedFebruary 28, 2025
09Completion periodnot published
10Tender reference numbernot published in any source opened
11Pre-bid estimated valuenot published in any source opened
12Status as recordedUnder construction; construction started June 13, 2025
13Status as at2025-03-31 (FY2024-25 annual report, signed 10.11.2025)
14Record typeOFFICIAL
15Source documentdicdl_ar25.pdf, page 24
16Plot area34,529 sq m
17Built up area6,082.11 sq m

Source: dicdl_ar25.pdf, page 24. Record type OFFICIAL. All rows last verified 2026-08-04 against the cited page.

02

What the document actually says

Quoted from the document, not paraphrased

The Integrated School project construction work was awarded to M/s Build Well Engineers on an EPC basis. The award date was February 28, 2025, with a project cost of ₹27.99 Crore. M/s TPF Engineering Pvt Ltd. serves as the Project Management Consultant (PMC). The school, adhering to CBSE/IB standards (Nursery to 12th Standard), covers a plot area of 34,529 square meters and a

Quoted from dicdl_ar25.pdf, page 24. Record type OFFICIAL. Retrieved 2026-08-04. The quotation is truncated exactly where the extraction truncated it and has not been tidied.

Value is stated as 'project cost'. PMC: M/s TPF Engineering Pvt Ltd.

03

How long the winner took to start

What can and cannot be measured here

The winner took 105 days from award to starting on site, measured by subtracting the award date from the construction start date, both of which the annual report prints. That is the only delivery measure this record supports. Because no completion date exists on the record, the work cannot be described as running late or running early by anyone, including DICDL.

Across the register, six of eleven awards carry both an award date and a construction start date, and none of the seventeen records carries a completion date. The comparison view for all of them is on the delivery schedule.

This is the only award held by Build Well Engineers in this register. Its sheet is at Build Well Engineers.

Source dicdl_ar25.pdf
Checked 2026-08-04
04

What is missing from this record

What is missing, stated plainly

  • GAP 01No tender reference number is published against this award in any source opened, so it cannot be joined to a tender notice.
  • GAP 02No pre-bid estimated contract value is published, so the bid against estimate variance cannot be computed.
  • GAP 03No contract duration and no scheduled completion date are published, so this contract cannot be shown as early, on time or late.

These gaps are taken from the dataset’s own declared gap list, filtered to the fields that are null on this record. They are not inferred. The complete list of seventeen contract gaps and eleven financial gaps is on the method sheet.

PUBLISHED2026-08-11
VERSIONC
HOW SOLID IS THISUNDER CONSTRUCTION
WHAT THIS PAGE ISIntegrated School
WHERE THE FIGURES COME FROMdicdl_ar25.pdf
AWARDED TOM/s Build Well Engineers
RECORD TYPEOFFICIAL