Food Court

Food Court was awarded to M/s. SCC Infrastructure on 2025-05-07 at a stated ₹17.47 Crore. Record type OFFICIAL, taken from dicdl_ar25.pdf, page 23. No completion date is published for this contract, so it cannot be reported as on time or late.

Award value17.47INR crore
Award date2025-05-07ISO
Construction start2025-06-04ISO
Scheduled completionno datanot published in any source
1.0

The record

SCH-FOO / CONTRACT RECORD / REV A / 2026-08-04
Every published field for the Food Court award. Source: DICDL annual report and the dataset field list
No.ItemFieldValue as recorded
01Work as described in the sourceFood Court, Dholera Activation Area - construction work. 8 kitchens/counters, 4 shops, seating for 600; land area 7,466.84 sq m; built-up area 2,981 sq m.
02Specification8 kitchens and counters, 4 shops, seating for 600 people
03Awarded to, as printedM/s. SCC Infrastructure
04Award basisEPC
05Project management consultantM/s TPF Engineering Pvt Ltd.
06Value as printed₹17.47 Crore
07Value unitINR crore
08Award date as printedMay 7, 2025
09Completion periodnot published
10Tender reference numbernot published in any source opened
11Pre-bid estimated valuenot published in any source opened
12Status as recordedUnder construction; construction started June 04, 2025
13Status as at2025-03-31 (FY2024-25 annual report, signed 10.11.2025)
14Record typeOFFICIAL
15Source documentdicdl_ar25.pdf, page 23
16Plot area7,466.84 sq m
17Built up area2,981 sq m
Source: dicdl_ar25.pdf, page 23. Record type OFFICIAL. All rows last verified 2026-08-04 against the cited page.
2.0

What the source actually says

Quoted from the document, not paraphrased

The Food Court project construction work was awarded to M/s. SCC Infrastructure on an EPC basis. The award date was May 7, 2025, and the total project cost is ₹17.47 Crore. M/s TPF Engineering Pvt Ltd. serves as the Project Management Consultant (PMC). The project aims to improve the region's livability. It covers a total land area of 7,466.84 square meters and has a bu

Quoted from dicdl_ar25.pdf, page 23. Record type OFFICIAL. Retrieved 2026-08-04. The quotation is truncated exactly where the extraction truncated it and has not been tidied.

Value is stated as 'total project cost'. PMC: M/s TPF Engineering Pvt Ltd. Award date falls after the 31 March 2025 balance-sheet date.

3.0

Delivery against declared dates

What can and cannot be measured here

The winner took 28 days from award to starting on site, measured by subtracting the award date from the construction start date, both of which the annual report prints. That is the only delivery measure this record supports. Because no completion date exists on the record, the work cannot be described as running late or running early by anyone, including DICDL.

Across the register, six of eleven awards carry both an award date and a construction start date, and none of the seventeen records carries a completion date. The comparison view for all of them is on the delivery schedule.

The same firm holds 1 other award in this register: Integrated Healthcare Facility. Its full sheet is at SCC Infrastructure.

SHEET FOO
REV A
DATE 2026-08-04
SOURCE dicdl_ar25.pdf
4.0

Declared gaps on this record

What is missing, stated plainly

  • GAP 01No tender reference number is published against this award in any source opened, so it cannot be joined to a tender notice.
  • GAP 02No pre-bid estimated contract value is published, so the bid against estimate variance cannot be computed.
  • GAP 03No contract duration and no scheduled completion date are published, so this contract cannot be shown as early, on time or late.

These gaps are taken from the dataset’s own declared gap list, filtered to the fields that are null on this record. They are not inferred. The complete list of seventeen contract gaps and eleven financial gaps is on the method sheet.

SHEETFOO
REVISIONA
DATE ISSUED2026-08-04
STATUSUNDER CONSTRUCTION
TITLEFood Court
SOURCEdicdl_ar25.pdf
AWARDED TOM/s. SCC Infrastructure
RECORD TYPEOFFICIAL