SCC Infrastructure holds 2 awards in the Dholera register: Integrated Healthcare Facility, awarded 2024-12-16. Its disclosed work is worth Rs. 151.15 crore across 2 priced awards. Record type OFFICIAL, verified 2026-08-04.
Awards held
| No.Item | Work | Basis | Award valueINR crore | Award dateISO | Construction startISO | State | Record |
|---|---|---|---|---|---|---|---|
| 01 | Integrated Healthcare Facility | EPC | 133.68 | 2024-12-16 | 2025-02-07 | UNDER CONSTRUCTION | OFFICIAL |
| 02 | Food Court | EPC | 17.47 | 2025-05-07 | 2025-06-04 | UNDER CONSTRUCTION | OFFICIAL |
| Source: dicdl_ar25.pdf. All rows last verified 2026-08-04 against the cited page. | |||||||
Named in the sources as
- Joint venture of M/s SCC Infrastructure and M/s P. R. Patel & Co.
- M/s. SCC Infrastructure
Firms are grouped under one normalised name so that awards can be counted per firm. The printed variants above are the exact strings the sources use, kept so a reader can find the row in the original document.
What the documents say about this firm
Quoted, not summarised
The Integrated Healthcare Facility project construction work was awarded to the joint venture of M/s SCC Infrastructure and M/s P. R. Patel & Co. on an EPC basis. The award date was December 16, 2024, and the total project cost is ₹133.68 Crore. M/s Hites serves as the Project Management Consultant (PMC). The facility covers a plot area of 9,668 square meters and has a built-up area of 15,
On Integrated Healthcare Facility, quoted from dicdl_ar25.pdf, page 22. Record type OFFICIAL.
The Food Court project construction work was awarded to M/s. SCC Infrastructure on an EPC basis. The award date was May 7, 2025, and the total project cost is ₹17.47 Crore. M/s TPF Engineering Pvt Ltd. serves as the Project Management Consultant (PMC). The project aims to improve the region's livability. It covers a total land area of 7,466.84 square meters and has a bu
On Food Court, quoted from dicdl_ar25.pdf, page 23. Record type OFFICIAL.
Delivery record
What this firm's dates support
Mobilisation, DERIVED as construction start minus award date: Integrated Healthcare Facility 53 days, Food Court 28 days. No completion date is published against any of this firm's Dholera work, so nothing here can be described as late.
The whole register's delivery view, including the empty due date column that applies to every firm equally, is on the delivery schedule. The complete list of firms is on the contractors sheet.