Build Well Engineers

Build Well Engineers holds 1 of the eleven Dholera awards on record: Integrated School, awarded 2025-02-28. Its disclosed work is worth Rs. 27.99 crore across 1 priced award. Everything on this page comes from a signed, audited annual report. Every row was last checked against the cited page on 2026-08-04.

01

What this firm has been given

Every Dholera award held by Build Well Engineers. Source: DICDL annual report and the contract dataset

Every Dholera award held by Build Well Engineers. Source: DICDL annual report and the contract dataset
No.ItemWorkBasisAward valueINR croreAward dateISOConstruction startISOStateRecord
01Integrated SchoolEPC27.992025-02-282025-06-13UNDER CONSTRUCTIONOFFICIAL

Source: dicdl_ar25.pdf. All rows last verified 2026-08-04 against the cited page.

Named in the sources as

  • M/s Build Well Engineers

Firms are grouped under one normalised name so that awards can be counted per firm. The printed variants above are the exact strings the sources use, kept so a reader can find the row in the original document.

02

The documents, quoted rather than summarised

Quoted, not summarised

The Integrated School project construction work was awarded to M/s Build Well Engineers on an EPC basis. The award date was February 28, 2025, with a project cost of ₹27.99 Crore. M/s TPF Engineering Pvt Ltd. serves as the Project Management Consultant (PMC). The school, adhering to CBSE/IB standards (Nursery to 12th Standard), covers a plot area of 34,529 square meters and a

On Integrated School, quoted from dicdl_ar25.pdf, page 24. Record type OFFICIAL.

03

How fast it got on site

What this firm's dates support

Mobilisation, DERIVED as construction start minus award date: Integrated School 105 days. No completion date is published against any of this firm's Dholera work, so nothing here can be described as late.

The whole register's delivery view, including the empty due date column that applies to every firm equally, is on the delivery schedule. The complete list of firms is on the contractors sheet.

Source dicdl_ar25.pdf
Checked 2026-08-04
PUBLISHED2026-08-11
VERSIONC
HOW SOLID IS THISUNDER CONSTRUCTION
WHAT THIS PAGE ISBuild Well Engineers
WHERE THE FIGURES COME FROMdicdl_ar25.pdf
AWARDS HELD1
DISCLOSED VALUE27.99 crore