Dholera Works Record
CONTRACTS 11 / OPEN TENDERS 6 / AUDITED FACTS 225 / UPDATED 2026-08-04 / REV A
SHEET FRM-KAMREV ASECTION 02 CONTRACTORS2026-08-04

Kamnath Private Limited

Kamnath Private Limited holds 1 award in the Dholera register: Tent City, awarded 2025-03-27. No rupee figure that DICDL pays is published against this firm anywhere in the sources opened, so its disclosed value is nil rather than zero. Record type OFFICIAL, verified 2026-08-04.

1.0

Awards held

SCH-FRM-KAM / FIRM RECORD / REV A / 2026-08-04
Every Dholera award held by Kamnath Private Limited. Source: DICDL annual report and the contract dataset
No.ItemWorkBasisAward valueINR croreAward dateISOConstruction startISOStateRecord
01Tent CityPPP (Public Private Partnership), 10-year operations periodnot published2025-03-272025-05-27UNDER CONSTRUCTIONOFFICIAL
Source: dicdl_ar25.pdf. All rows last verified 2026-08-04 against the cited page.

Named in the sources as

  • M/s Kamnath Private Limited

Firms are grouped under one normalised name so that awards can be counted per firm. The printed variants above are the exact strings the sources use, kept so a reader can find the row in the original document.

2.0

What the documents say about this firm

Quoted, not summarised

The Tent City project construction work was awarded to M/s Kamnath Private Limited on a PPP (Public Private Partnership) basis with 10-year operations period. The award date was March 27, 2025, with management fees of ₹1.55 Crore receivable by DICDL. The project aims to create an eco-luxury retreat for business and leisure travellers. The Construction work of the proje

On Tent City, quoted from dicdl_ar25.pdf, page 27. Record type OFFICIAL.

3.0

Delivery record

What this firm's dates support

Mobilisation, DERIVED as construction start minus award date: Tent City 61 days. No completion date is published against any of this firm's Dholera work, so nothing here can be described as late.

The whole register's delivery view, including the empty due date column that applies to every firm equally, is on the delivery schedule. The complete list of firms is on the contractors sheet.

SHEET FRM-KAM
REV A
DATE 2026-08-04
SOURCE dicdl_ar25.pdf
SHEETFRM-KAM
REVISIONA
DATE ISSUED2026-08-04
STATUSUNDER CONSTRUCTION
TITLEKamnath Private Limited
SOURCEdicdl_ar25.pdf
AWARDS HELD1
DISCLOSED VALUEnone