Dholera Contracts
11 awards with a named winner / 6 tenders still open / Updated 2026-08-04

Which companies won government work at Dholera, and for how much

Cube Construction Engineering Limited

Cube Construction Engineering Limited holds 1 of the eleven Dholera awards on record: ABCD Building, awarded on a date no source publishes. Its disclosed work is worth Rs. 72.31 crore across 1 priced award. Everything on this page comes from a signed, audited annual report. Every row was last checked against the cited page on 2026-08-04.

01

What this firm has been given

Every Dholera award held by Cube Construction Engineering Limited. Source: DICDL annual report and the contract dataset

Every Dholera award held by Cube Construction Engineering Limited. Source: DICDL annual report and the contract dataset
No.ItemWorkBasisAward valueINR croreAward dateISOConstruction startISOStateRecord
01ABCD BuildingEPC72.31not publishednot publishedIN DISPUTEOFFICIAL

Source: dicdl_ar25.pdf. All rows last verified 2026-08-04 against the cited page.

Named in the sources as

  • M/s. Cube Construction Engineering Limited (CCEL)

Firms are grouped under one normalised name so that awards can be counted per firm. The printed variants above are the exact strings the sources use, kept so a reader can find the row in the original document.

02

The documents, quoted rather than summarised

Quoted, not summarised

B. The Company had awarded contract for Design and Construction of Administration and Business Centre of Dholera (ABCD) Building in DSIR, Dholera on EPC Basis to M/s. Cube Construction Engineering Limited (CCEL) with contract amount of 72,31,11,111/-. CCEL has raised following claims: Claim No. 01 :- Cost Incurred as Result to Build Up Area Being More Than Contract (Cost Amount: Rs. 20,16,11,451/-) Claim No. 02 :- Cos

On ABCD Building, quoted from dicdl_ar25.pdf, page 100. Record type OFFICIAL.

This firm has raised claims against DICDL on its Dholera contract, disclosed under contingent liabilities. The detail is on the disputes sheet.

03

How fast it got on site

What this firm's dates support

No mobilisation figure can be derived for this firm because the published record is missing an award date, a construction start date or both. Nothing has been estimated to fill the gap.

The whole register's delivery view, including the empty due date column that applies to every firm equally, is on the delivery schedule. The complete list of firms is on the contractors sheet.

Source dicdl_ar25.pdf
Checked 2026-08-04
PUBLISHED2026-08-11
VERSIONC
HOW SOLID IS THISIN DISPUTE
WHAT THIS PAGE ISCube Construction Engineering Limited
WHERE THE FIGURES COME FROMdicdl_ar25.pdf
AWARDS HELD1
DISCLOSED VALUE72.31 crore